Horsham Gates

Horsham Gates
15 contemporary 1 & 2 bedroom, new build apartments, finished to a high quality specification.

Employed as the main contractor, Horsham Gates 3 Extension, this new property was an extension to an existing Permitted Development conversion scheme. Built using piled foundations with an RC podium slab and a CLT (Cross Laminated Timber) superstructure to form 3 storeys of residential accommodation on top.

The new build property covered 12,250sqft and was directly adjacent (within 5m) of Horsham Railway Sidings.

Services provided:  Main Contracting Design & Build

Client:  CCL Develco 2 Ltd

Construction value:  £2.8 million

Project summary:

Start date:
March 2017

Completion date:
May 2018

Architects:
WCEC Architects

Structural Engineers:
BWB Consulting Ltd

Mechanical & Electrical:
BWB Consulting Ltd

Project managers:
DBK Partners Ltd

More details:

We led the design team and worked closely with Network Rail on this logistically complex scheme. We were initially appointed using a Pre-Construction Services Agreement (PCSA) for stage 1 (design development); Stage 2 (construction) was delivered using a JCT DB 2016 form of contract.

Outputs that we produced from the PCSA included the Employer’s Requirements, Construction Programme and fully detailed fixed price.

The total period for design development and construction was 19 months to completion. This new build element was the final phase of a total redevelopment of the prestigious Horsham Gates landmark site.